In Lee Ming Yueh v Broadway-Nassau Investments Ltd ([2012] 5 HKLRD 208, CA) water leaked through the walls and roof of a top floor flat. The managers asked contractors to look at the problem. Initial remedial efforts were not effective but eventually the problem was identified and resolved. The water seepage damaged the walls and floor of the flat. The owner of the flat claimed damages against the managers and the incorporated owners alleging breach of the Deed of Mutual Covenant and section 18 of the Building Management Ordinance (imposing duties on the Manager and the incorporated owners to keep common parts in repair). The claim failed both in the Lands Tribunal and in the Court of Appeal. The duty was one of ‘proper management’. The managers had promptly engaged contractors to investigate and remedy the problems when they received complaints. They could not delegate their duty to contractors but there was nothing to suggest that they had been negligent in their choice of contractor.